Texas regulators have authorized a major expansion of a natural gas-fired power plant designed to supply electricity to a $25-billion artificial intelligence data center development near Abilene.

The Texas Commission on Environmental Quality approved the expansion Nov. 19, allowing Houston-based VoltaGrid to increase generating capacity at its ABI-1 facility from 709 MW to 2,582 MW. The permit replaces an earlier authorization for 210 natural gas engines with one covering 620.

The power plant will serve Frontier, Vantage Data Centers’ largest campus worldwide, a planned 1,200-acre development in West Texas’ Shackelford County. Spanning nearly two square miles, the $25-billion project will include 10 data centers totaling 3.7 million sq ft and 1.4 GW of critical computing capacity. Part of the Oracle and OpenAI Stargate initiative, Frontier will receive dedicated electricity from a generating facility owned and operated separately by VoltaGrid.

Under the Nov. 19 authorization, VoltaGrid can construct 10 independently operating power blocks using Jenbacher reciprocating engines. State construction filings identify Kiewit as the design firm for buildings at Frontier, including a 344,796-sq-ft data center with an estimated construction cost of $950 million and a projected completion in August 2027. The filings do not establish Kiewit’s role in VoltaGrid’s separately owned generating facility.

According to TCEQ’s technical review, the configuration includes 250 Jenbacher J620 engines rated at 3.22 MW each and 370 J624 engines rated at 4.80 MW each. VoltaGrid will group the engines in its proprietary QPac modular generating assemblies, each accommodating up to four J620 engines or five J624 engines, along with associated generators and emissions controls. Manufacturer INNIO describes the five-engine J624 configuration as a roughly 25-MW unit designed for rapid deployment and incremental expansion of data center power capacity.

For large modular power installations, the work extends beyond positioning generators on-site. During a Nov. 10 ENR visit to microgrid supplier Mesa Power Solutions‘ San Antonio manufacturing facility, CEO Scott Gromer explained that his company’s scope typically begins where the natural gas supply reaches its equipment and ends at the electrical switchgear.

“Bring us the gas, take away the electricity for the generation piece,” he said.

Gas pipelines, electrical distribution systems and connections to the data center must be coordinated with the generating equipment. At Frontier, the contractors responsible for those portions of the work have not been identified. Mesa is not involved in the project.

Top: Exterior view of a green INNIO Jenbacher Type 6 gas engine-generator. Bottom: Labeled conceptual cutaway showing the generator, V-configured engine, pistons, crankshaft and supporting systems.

Top: INNIO’s Jenbacher Type 6 gas engine-generator set, part of the company’s lineup of natural gas-fired power generation equipment. Bottom: A conceptual cutaway illustrates the generator, engine coupling, V-configured cylinders, crankshaft, turbocharging and cooling systems. The rendering is schematic and does not represent a manufacturer-verified internal configuration.

Top: Image courtesy INNIO
Bottom: AI-generated illustration by OpenAI for ENR; conceptual rendering.

Supporting infrastructure will include 60 natural gas-fired heaters to condition fuel arriving through a pipeline, 20 diesel-powered black-start engines to restart generating equipment after outages, and four bulk urea storage tanks serving the emissions-control systems. Each generating block will also have lubricating-oil storage and associated fuel and electrical equipment.

To control nitrogen oxide emissions, the permit requires selective catalytic reduction systems, along with oxidation catalysts to reduce carbon monoxide and volatile organic compounds. TCEQ’s analysis projects potential annual emissions of approximately 10.63 million tons of carbon dioxide equivalent under the permitted operating configuration, along with allowable annual emissions of approximately 570 tons of nitrogen oxides and 372 tons of formaldehyde. These figures represent modeled or permitted emissions, not measured pollution from operating equipment.

Permitting Questions and Legal Scrutiny

Approval followed Texas’ Nov. 13 resumption of data center permitting after a statewide pause Gov. Greg Abbott imposed in September. TCEQ had issued a preliminary approval notice for VoltaGrid’s ABI-1 facility Sept. 22, one day after the directive, according to regulatory records examined by environmental watchdog groups. Whether the application was subsequently suspended remains unclear.

Under federal Title V operating-permit requirements administered by TCEQ, VoltaGrid must submit an initial application before beginning operations, according to the agency’s technical review.

Separately, Vantage and VoltaGrid face federal litigation over permitting for gas-fired generating facilities serving two data center campuses in San Antonio. The Environmental Integrity Project, Sierra Club and Public Citizen allege the companies proceeded under permits intended for smaller pollution sources rather than obtaining the major-source authorizations required by federal law. The lawsuit does not involve the Frontier development.

“Vantage and VoltaGrid want to come into this Texas neighborhood and dump thousands of tons of air pollutants into an already smoggy community—and they want to do it without the proper permits or even hearing what impacted people have to say,” Josh Smith, senior attorney for the Sierra Club’s Environmental Law Program, said in a statement.

Although the new authorization establishes the full generating configuration, regulatory records do not establish how many engines have been installed or commissioned, which contractors are building the plant or when the additional generating blocks will enter service.