Alberta is proposing to keep large data centres at least 600 metres from homes, restrict development on prime farmland and impose new water-use standards under legislation introduced Wednesday, Nov. 18.

Technology and Innovation Minister Nate Glubish said approximately 30 per cent of current data-centre proposals could be affected by the changes, although he could not immediately provide a breakdown of the projects by size.


Related Stories:


Bill 42, the Energy, Environment and Utilities Statutes Amendment Act, 2026, would give the Alberta Utilities Commission (AUC) authority to approve and regulate large data centres.

The government intends to apply the new approval requirements to facilities with a maximum electricity demand of 10 megawatts or more.

That threshold, the proposed 600-metre setback and other development requirements would be established through regulations rather than being specified directly in the legislation.

Glubish said Alberta remains interested in attracting investment but is prepared to turn away projects that cannot meet its standards.

“And if that means some investment leaves Alberta, we can live with that,” he said during Wednesday’s news conference.

Why Alberta chose 600 metres

Under the proposal, large data centres would generally have to be located at least 600 metres from the nearest home.

Affordability and Utilities Minister R.J. Sigurdson said the distance would be measured from the boundary of a proposed development to the edge of the nearest dwelling.

Journalists repeatedly questioned how the government settled on that distance.

Glubish said officials examined setbacks used for other industrial developments and considered advice from engineers and regulators. He argued that substantially greater distances could make industrial development impractical in parts of Alberta.

Sigurdson pointed to existing power-generating facilities near Calgary communities as examples of major industrial operations located at comparable distances from residential areas.

He said the proposed setback, combined with noise and lighting requirements, would provide appropriate protection. The ministers did not present a specific supporting study during the news conference.

Municipalities could establish greater setbacks within their boundaries, according to Glubish.

The proposed regulations could also allow municipalities to request exceptions or changes to the provincial setback where local planning supports development.

Municipal land-use rules would continue to apply, meaning a project meeting the provincial minimum would not automatically qualify for local development approval.

Bill 42 would also expand the AUC’s authority beyond the electricity-generating infrastructure associated with data centres.

The commission would oversee approvals for qualifying large data centres and apply provincial noise and lighting requirements directly to those facilities.

Glubish said those enforcement powers would continue after construction, allowing the commission to intervene if an operating facility failed to meet its requirements.

Sigurdson said data centres below the proposed 10-megawatt threshold would continue through municipal development approval processes.

Other provincial requirements, including those governing associated power generation, water use and environmental approvals, could still apply.

Prime farmland restrictions would include exceptions

The government also wants to restrict large data centres on Alberta’s most productive agricultural land.

The proposed measures would cover Class 1 and Class 2 farmland, along with Class 3 agricultural land in municipalities where neither of the higher classifications is available.

Currently irrigated farmland would also be subject to restrictions.

The province estimates approximately 14 million acres of prime agricultural land would be protected.

Glubish said exceptions would be available for designated industrial zones and previously developed industrial sites. He also identified existing power-generation locations as areas where the province wants to encourage development.

Bill 42 would require cabinet approval for data centres on land designated as high-quality agricultural land, subject to the legislation’s exemptions.

Cabinet could authorize development on that land.

However, that particular approval requirement would cease to have effect on Sept. 20, 2027.

The date does not mean other agricultural restrictions would automatically expire. Requirements established through separate regulations could remain in effect.

The province has yet to finalize the land classifications and other conditions that would govern development under the proposed rules.

What happens to existing proposals?

The timing of the restrictions drew questions because Alberta has already encouraged companies to pursue major data-centre investments.

Glubish defended the government’s approach, saying existing regulatory processes provided safeguards while public consultations helped identify areas where further protection was needed.

The province says its proposals followed four public town halls held in August and September, a government survey and other feedback.

Projects already moving through approval processes could receive different treatment under the new rules.

Glubish cited existing AUC decisions or proceedings, signed transmission agreements and municipal development permits as circumstances relevant to exemptions for earlier projects.

However, those examples do not establish that a project would automatically qualify.

Bill 42 would allow exemptions based on how far construction or operations had progressed when the new approval rules took effect. The government would establish the qualifying stages through regulation.

Separately, operators already building or operating covered data centres when the new provisions took effect would be treated as holding AUC approval under the new system.

They would still have to comply with other applicable requirements.

The province has not identified which proposals would qualify for exemptions.

Glubish’s estimate that approximately 30 per cent of proposals could be affected does not establish how many developments would ultimately be refused approval.

Alberta’s Opposition New Democrats criticized the proposed restrictions Thursday and renewed their call for a pause on all AI data-centre projects.

“The Alberta NDP upholds our call for a pause on all AI data centre projects until a comprehensive, community-supported plan is in place,” technology and innovation critic Nathan Ip said in a Nov. 19 statement.

The minister also acknowledged that some proposed developments were unlikely to proceed regardless of the new restrictions.

“Not all of them were real,” he said.

Glubish distinguished developers undertaking substantial engineering and regulatory work from others he described as pursuing speculative land-development opportunities.

He said he would consider it a positive outcome if less serious proposals left the development pipeline.

Glubish did not identify individual projects in either category.

He also clarified that Alberta’s AI Data Centre Concierge Program helps developers understand regulatory requirements. Participation does not constitute provincial approval or endorsement.

Water-use standards remain unfinished

Alberta is proposing a mandatory efficiency standard intended to bring water used for data-centre cooling close to zero.

Glubish said the requirements would effectively prohibit water-intensive cooling technologies, including evaporative cooling.

“This won’t just be a guideline or a best practice; it will be the law,” he said.

The province has not yet established a numerical threshold for near-zero water consumption.

Canadian Press journalist Lisa Johnson questioned how the government intended to define the standard when the requirements would be set through regulations.

Glubish said the province wants to establish minimum efficiency requirements rather than mandate one cooling technology.

He argued that prescribing specific equipment could prevent operators from adopting more efficient alternatives as technology improves.

The government also proposes requiring companies to measure and report their water consumption and comply with provincial monitoring requirements.

Large data centres would have to be designed and operated so excess heat could be recovered and made available for use by greenhouses, industrial facilities or homes.

The Ministry of Environment and Protected Areas would continue overseeing water licences and environmental approvals.

The proposed cooling-water standard would not determine how much water an electricity-generating facility built to supply a data centre could consume. Those operations would remain subject to applicable provincial water requirements.

How would electricity customers be protected?

Bill 42 would also create a new designation for qualifying data-centre electricity systems.

It would allow operators to use electricity generated within their developments without first selling that power into Alberta’s electricity market.

The owners of designated systems would also be responsible for specified transmission infrastructure costs rather than having those costs included in charges recovered from other electricity customers.

To qualify, a system would need at least one generating unit on the property intended to supply the development.

It would also have to meet a separate condition governing its maximum electricity demand directly from the transmission grid.

That threshold would be 75 megawatts or a lower amount established by the Alberta Electric System Operator.

The AUC would assess whether the proposed arrangement could maintain or improve grid reliability and whether the system’s owners would cover the associated transmission infrastructure costs.

These conditions are separate from the proposed 10-megawatt threshold for general data-centre approvals.

Sigurdson said the designation builds on arrangements already available to major industrial operations that generate electricity for their own use.

Asked what the changes would add to Alberta’s existing policies, he said they would give operators greater flexibility to distribute electricity within large developments.

He also reiterated the government’s commitment to protecting electricity customers from data-centre costs.

“The cost of data centers wasn’t going to be passed on to ratepayers,” he said.

Existing provincial rules already require large data-centre developers to pay certain costs associated with connecting to Alberta’s electricity grid.

According to the province, data centres must also reduce their electricity consumption during grid emergencies before households and essential services are asked to do so.

Bill 42 would address specified infrastructure costs. Those protections do not, by themselves, determine how additional electricity demand might affect broader market prices.

The Alberta Electric System Operator would continue assessing whether proposed grid connections could be accommodated without compromising reliability.

Public participation and provincial oversight

Expanding the AUC’s authority would bring large data centres into the commission’s existing process for reviewing applications and receiving input from affected parties.

Glubish said residents would be able to raise concerns through that process.

The legislation would also bring data centres within provisions requiring the commission to consider social, economic and environmental effects when assessing the public interest during hearings or other proceedings.

However, the commission would not be required to hold a hearing for every application.

Bill 42 would extend existing provisions allowing the commission to proceed without a hearing in specified circumstances, including where applicants meet applicable requirements concerning landowners who could be directly and adversely affected.

The legislation would also limit what could be considered in a particular public-interest assessment under the Hydro and Electric Energy Act.

A data centre’s computing activities and how its data is used would not be factors in that assessment.

The restriction concerns the scope of the regulatory review. It does not, by itself, exempt operators from privacy legislation or other applicable laws.

Although the government’s announcement focuses on artificial intelligence, the proposed statutory definition of a data centre is broader. It includes facilities used for cloud computing, data hosting, digital asset mining and other digital services.

Sturgeon County Mayor Alanna Hnatiw welcomed progress on the regulatory framework in a statement included in the provincial news release.

However, she said the county would continue advocating for action on cumulative transportation impacts, emissions, stakeholder engagement, responsible use of artificial intelligence, digital privacy and digital sovereignty.

Bill 42 received first reading in the Alberta legislature Wednesday.

The proposed restrictions are not yet law.

If the legislation passes, the province would still have to establish detailed requirements governing setbacks, agricultural land, water efficiency and exemptions for existing developments.

Those regulations and commission rules would be developed with municipalities, industry, Indigenous communities and Albertans, according to the government.

 

Get the facts

Add OkotoksOnline as a Preferred Source on Google to see more of our stories in your search.



Source link